August & September 2006 Newsletter
Cluster K1 List of Completed Activities (up to 28 September 2006)
- Filling behind the concrete slabs for 80% (Photo No.1, 2, 3).
- Demobilization of the Diaphragm wall Equipments and cleaning the site going on.
List of ongoing activities (Up to 28 September 2006)
- Installation and stressing of the Anchors.
- Installation and running the dewatering system.
Cluster K2 List of Completed Activities (up to 28 September 2006)
- Filling behind the concrete slabs for 100% (Photo No.4, 5).
- Demobilization of the Diaphragm wall Equipments going on (Photo No.6).
List of ongoing activities (Up to 28 September 2006)
- Installation and stressing of the Anchors.
- Installation and running the dewatering system.
Cluster K3 List of Completed Activities (up to 28 September 2006)
- Demobilization of the Diaphragm wall Equipments going on (Photo No.7, 8).
List of ongoing activities (Up to 28 September 2006)
- Installation and stressing of the Anchors.
- Installation and running the dewatering system.
Al Attar Business Tower, 2nd Floor, Sheikh Zayed Road
P.O.Box 333700, Dubai, United Arab Emirates
Tel: + 971 4 332 2233, Fax: +971 4 332 8433
Email: info@alattargroup.com
Websites: www.the-skyscraper.com, www.alattargroup.com
|