June & July 2006 Newsletter
With reference to our April-May Newsletter , We would like to inform our valued customers and clients for issuing of June-July Newsletter. We appreciate to have your feedback and comments in this regards.
Cluster K1 List of Completed Activities (up to 30 July 2006)
- Installation of all the Diaphragm wall.
- Casting of 60% of the capping beam with 1 section and concrete Slabs (Photo No.1, 2).
- Excavation works from the existing level at +5.80 DMD up to the level of +0.50 DMD. (Photo No.3).
List of ongoing activities (Up to 30 July 2006)
- Casting of 40% of the capping beam.
- Filling behind the concrete slabs for 20% (Ramp area).
Cluster K2 List of Completed Activities (up to 30 July 2006)
- Installation of all the Diaphragm wall (Photo No.4, 5).
- Casting of 85% of the capping beam with 1 section and concrete Slabs (Photo No.6, 7).
- Excavation works from the existing level at +4.20 DMD up to the level of +0.50 DMD.
List of ongoing activities (Up to 30 July 2006)
- Casting of 15% of the capping beam.
- Excavation works from the level at +0.50 DMD up to the final level at -11.30 DMD.
Cluster K3 List of Completed Activities (up to 30 July 2006)
- Installation of all the Diaphragm wall (Photo No.8).
- Casting of 20% of the capping (Photo No.9, 10).
- Excavation works from the existing level at +4.20 DMD up to the level of +0.50 DMD.
List of ongoing activities (Up to 30 July 2006)
- Casting of 80% of the capping beam.
- Filling behind the concrete slabs.
- Excavation works from the level at +0.50 DMD up to the final level at -14.40 DMD.
Al Attar Business Tower, 2nd Floor, Sheikh Zayed Road
P.O.Box 333700, Dubai, United Arab Emirates
Tel: + 971 4 332 2233, Fax: +971 4 332 8433
Email: info@alattargroup.com
Websites: www.the-skyscraper.com, www.alattargroup.com
|